MRIP Monthly Report - January 2017 |
Testing for Measurement Error in a Recreational Fishing Mail Survey |
TASK # |
PREREQUISITE |
MILESTONE |
STATUS |
DESCRIPTION |
PLANNED START DATE |
PLANNED END DATE |
START DATE |
END DATE |
NOTE |
1 | | Y | Complete | Award data collection contract | 14-FEB-14 | 14-FEB-14 | 14-FEB-14 | 14-FEB-14 | |
2 | | Y | Complete | Finalize Validation Study instrument | 18-APR-14 | 18-APR-14 | 18-APR-14 | 30-APR-14 | The final survey instrument and data collection protocols were developed by the contractor and submitted to OMB for approval. |
3 | | Y | Complete | Initiate Validation Study data collection | 01-MAY-14 | 01-MAY-14 | 01-MAY-14 | 01-MAY-14 | Data collection was implemented the week of 5/5 and will continue through July or August. |
4 | | Y | Complete | Receive Validation Study final deliverables | 31-OCT-14 | 31-OCT-14 | 24-OCT-14 | 24-OCT-14 | |
5 | | Y | In Progress | Validation study final report | 31-DEC-14 | 31-DEC-14 | 01-JAN-15 | 28-FEB-17 | Analysis has been delayed by roll-out of new effort survey. |
600
600
3
1
False
False
False
False